6'Triggerpoint for fallprotectionrequired?ElectricalShould bedeenergizedprior toworking onor nearLightingJobsitesshould haveproper ____GlovesShould beworn whenworking withsharpobjects.LadderShould beset upcorrectlybefore using.Substitution2nd step inthehierarchyof controls.Slips/FallsGoodhousekeepinghelps preventthis.MedGasThis utilitycan befound inthe hospitalelimination1st andpreferredstep in thehierarchy ofcontrols.HolesMust becoveredandlabeledPTPRequireddaily priorto the startof workRadiationKnownpotentialhazard in theradiologydept.Material&ladderOver 8'long shouldbe carriedby 2 peoplePowderactuatedYou mustbe certifiedto use thistoolFaceshieldIs requiredwhen usinga chop sawor grinder.2-1/2moreinjurieswhen a PTPis not usedmetatarsalfootguardsType of PPErequiredwhen usinga jackhammerExcavationpermitRequiredwheneverany dirt isbeingdisturbedSilicaCan causesilicosis ifnotcontrolledPayattention!Is not anacceptableresponseon a PTPHearingprotectionPPE that isonly requiredwhen noiseis @ 85sB orhigherHousekeepingShould bedonethroughoutthe day onsite.Hierarchyofcontrols5 levels ofactions toreduce orremovehazardsScaffoldMust beInspected by cacompetentperson & greentagged prior touse.LOTOUsed toensureutilities aresafe to workon or around.ForemanWho isresponsiblefor thePTP?SubcontractorWho mustalso fillout a PTPdaily?DemoplanThis isrequiredprior toany demoFireExtinguisherRequired onevery projectand must becheckedmonthly6'Triggerpoint for fallprotectionrequired?ElectricalShould bedeenergizedprior toworking onor nearLightingJobsitesshould haveproper ____GlovesShould beworn whenworking withsharpobjects.LadderShould beset upcorrectlybefore using.Substitution2nd step inthehierarchyof controls.Slips/FallsGoodhousekeepinghelps preventthis.MedGasThis utilitycan befound inthe hospitalelimination1st andpreferredstep in thehierarchy ofcontrols.HolesMust becoveredandlabeledPTPRequireddaily priorto the startof workRadiationKnownpotentialhazard in theradiologydept.Material&ladderOver 8'long shouldbe carriedby 2 peoplePowderactuatedYou mustbe certifiedto use thistoolFaceshieldIs requiredwhen usinga chop sawor grinder.2-1/2moreinjurieswhen a PTPis not usedmetatarsalfootguardsType of PPErequiredwhen usinga jackhammerExcavationpermitRequiredwheneverany dirt isbeingdisturbedSilicaCan causesilicosis ifnotcontrolledPayattention!Is not anacceptableresponseon a PTPHearingprotectionPPE that isonly requiredwhen noiseis @ 85sB orhigherHousekeepingShould bedonethroughoutthe day onsite.Hierarchyofcontrols5 levels ofactions toreduce orremovehazardsScaffoldMust beInspected by cacompetentperson & greentagged prior touse.LOTOUsed toensureutilities aresafe to workon or around.ForemanWho isresponsiblefor thePTP?SubcontractorWho mustalso fillout a PTPdaily?DemoplanThis isrequiredprior toany demoFireExtinguisherRequired onevery projectand must becheckedmonthly

PTP - Call List

(Print) Use this randomly generated list as your call list when playing the game. There is no need to say the BINGO column name. Place some kind of mark (like an X, a checkmark, a dot, tally mark, etc) on each cell as you announce it, to keep track. You can also cut out each item, place them in a bag and pull words from the bag.


1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
  1. Trigger point for fall protection required?
    6'
  2. Should be deenergized prior to working on or near
    Electrical
  3. Jobsites should have proper ____
    Lighting
  4. Should be worn when working with sharp objects.
    Gloves
  5. Should be set up correctly before using.
    Ladder
  6. 2nd step in the hierarchy of controls.
    Substitution
  7. Good housekeeping helps prevent this.
    Slips/Falls
  8. This utility can be found in the hospital
    Med Gas
  9. 1st and preferred step in the hierarchy of controls.
    elimination
  10. Must be covered and labeled
    Holes
  11. Required daily prior to the start of work
    PTP
  12. Known potential hazard in the radiology dept.
    Radiation
  13. Over 8' long should be carried by 2 people
    Material & ladder
  14. You must be certified to use this tool
    Powder actuated
  15. Is required when using a chop saw or grinder.
    Face shield
  16. more injuries when a PTP is not used
    2-1/2
  17. Type of PPE required when using a jack hammer
    metatarsal foot guards
  18. Required whenever any dirt is being disturbed
    Excavation permit
  19. Can cause silicosis if not controlled
    Silica
  20. Is not an acceptable response on a PTP
    Pay attention!
  21. PPE that is only required when noise is @ 85sB or higher
    Hearing protection
  22. Should be done throughout the day on site.
    Housekeeping
  23. 5 levels of actions to reduce or remove hazards
    Hierarchy of controls
  24. Must be Inspected by ca competent person & green tagged prior to use.
    Scaffold
  25. Used to ensure utilities are safe to work on or around.
    LOTO
  26. Who is responsible for the PTP?
    Foreman
  27. Who must also fill out a PTP daily?
    Subcontractor
  28. This is required prior to any demo
    Demo plan
  29. Required on every project and must be checked monthly
    Fire Extinguisher